NEVP Phase I Update and SDG&E Delays by api-78283810 is a document available to read on EtoBox.
What is NEVP Phase I Update and SDG&E Delays about?
- The letter from the Unified Port of San Diego to SDG&E discusses delays caused by SDG&E to the North Embarcadero Visionary Plan (NEVP) Phase I project. - SDG&E delays have pushed the completion date of the project from September 2013 to February 2014, increasing costs. - The letter requests SDG&E commit to completing work by certain deadlines in September to help the project move forward, and discusses coordinating costs from the delays.