Can I read Time Schedule Progress and Notes on EtoBox?

Time Schedule Progress and Notes by Yasser Anis is a document available to read on EtoBox.

What is Time Schedule Progress and Notes about?

The project is currently at 0% progress in both PO stage and execution, requiring immediate action to avoid penalties. Shop drawing submissions for each floor and material submissions both have a duration of 3 working days, with an additional 5 days for coordination and consultant approval. Timely delivery is essential as outlined in the attached list.

Author
Yasser Anis
Language
EN