Third Party Inspection Report for PWSS by sonowal.kunal123 is a document available to read on EtoBox.

The site inspection report for the No.1 Namgharia PWSS under the Jal Jeevan Mission indicates that all work has been completed as of June 29, 2024, with a total project cost of Rs. 92.93 lakhs. The inspection, conducted by Bureau Veritas India Pvt. Ltd., confirmed that all proposed facilities, including 164 functional household tap connections, were installed as per the approved specifications. Additionally, various infrastructure components such as treatment plants, pump houses, and distribution networks w