The document describes the equipment and power requirements for two cogeneration power plants. The first is a 19.8 MW plant with a 125 TPH boiler requiring approximately 1400 kW for auxiliary power. It lists the loads for the turbine, water treatment plant, and flue gas handling system. The second plant produces 18 MW total with one 10 MW and one 8 MW turbine. It has two 50 TPH boilers each requiring approximately 535 kW for auxiliary power. Loads are listed for the turbines, cooling tower, water treatment,