Mobilization and Secured Advances in Construction by Jan Zeb is a document available to read on EtoBox.

Mobilization advance is given to contractors for civil construction projects to activate their physical and manpower resources for transfer to the construction site until project completion. It is normally 15% of the total contract value. The contractor must provide a bank or insurance guarantee equal to the advance amount and the advance is deducted from contractor bills in equal installments over the project period. Upon recovery completion, the guarantee is released. Secured advances up to 75% of materia