Ca Na LNG Power Center Reclamation Plan by william pasamonte is a document available to read on EtoBox.

This document outlines the methodology for a land reclamation project in three phases: 1) Site preparation including setting boundaries and transporting 1.88 million cubic meters of fill material by truck to reclaim 121,520 square meters of land. 2) Simultaneous land filling and construction of a shoreline protection structure using quarry rock and armor stones placed by excavator and barge. 3) Mud removal during filling using dredging equipment and disposal at an approved site.