Adama Town WSSI Project Monitoring Report by henoktefera57 is a document available to read on EtoBox.

The monitoring team conducted a field visit to assess progress of the Adama Town Water Supply and Sanitation Project. They found that while source development is progressing with 12 of 14 planned boreholes completed, major delays have occurred. Reinforcing steel and pipes have not been supplied for reservoirs and crossings. The contractor has frequently requested extensions and changes but lacks dedication. To ensure project success, close follow up is needed from all stakeholders to address bottlenecks and