March 2016 Layer House Installation Report by cris guzon is a document available to read on EtoBox.
What is March 2016 Layer House Installation Report about?
The monthly report from Bounty Farms summarizes progress made in March 2016 on installing layer houses three, four, and five at their San Pascual Farm location. House three installation was 100% complete, while house four installation was ongoing since February 10. House five was still in the flooring stage. The report provides percentage completion details for each part of the installation process for house three, such as the cage frame, wire partition, and drinker system all being 100% complete.