Fire Water Pump Upgrade Schedule by Satheesh Purushothaman is a document available to read on EtoBox.
The document outlines a schedule for upgrading the fire protection system at an existing power plant in Salalah, Oman. It involves installing a new fire water pump performance test facility over 24.5 days from October 15th to November 8th 2017. The work is divided into multiple teams installing piping, valves, and headers for 5 electric pumps, with tasks including isolating lines, cutting, welding, painting, and fixing supports. Testing of the fire pump performance is scheduled for November 7-8 after instal