The Nihaz School project is scheduled to start on April 5, 2025, and finish by July 17, 2025, with a total duration of 68 days. As of May 10, 2025, the project has achieved 15.07% of the planned work, resulting in a Schedule Performance Index (SPI) of 0.60, indicating that the project is behind schedule. The planned cumulative progress is 69.98%, while the actual cumulative progress is only 26.67%.