NR-32 Road Design Engineer Hours Justification by azam1u is a document available to read on EtoBox.
The memorandum from the Principal Engineer to the General Manager discusses the charging of man-hours for the NR-32 road design project. It states that only 221 out of 400 hours have been charged, which is deemed justified for the completion of 18 drawings for 3 bridges. A request is made for the acceptance of the charged hours.