St. Clair Project Lessons for Transit City by dbircs is a document available to read on EtoBox.

The summary analyzes lessons learned from implementing streetcar improvements on St. Clair Street in Toronto. Key issues with the St. Clair project included escalating costs from $48 million to over $106 million, delays in completion from the planned timeframe to over 5 years, and disruption to local communities and businesses during construction. Lessons identified include the need for improved project management, contracting strategies, budget and schedule controls, coordination between city departments,