Can I read Sunway Gandaria Bangi Project Update on EtoBox?

Sunway Gandaria Bangi Project Update by Mohd Jamal Mohd Moktar is a document available to read on EtoBox.

What is Sunway Gandaria Bangi Project Update about?

This document provides a project summary and progress report for the Sunway Gandaria Bangi project from March 2018 to April 2018. It shows that physical progress was 41% in April, a 2% variance from the scheduled 43%. The main delay was incomplete structure work at Zone 3 above level 9. To catch up, some trades will start earlier than scheduled. A summary of monthly physical progress, concrete volumes, payment claims, and an S-curve are also included.