Elevator Sump Pump Code Clarification by HA is a document available to read on EtoBox.
The document provides clarification on sump pump and drain requirements for elevator pits during a transition period between old and new code standards. Specifically: 1. If construction started before October 1, 2018, the former WAC rule applies regarding sump pumps and drains. 2. If construction started on or after October 1, 2018, the new ASME/CSA code requirements apply. 3. For projects where the design was already under the old rule but construction started after the new rules, a variance may be consi