Effluent Treatment Plant Progress Report by zebmech is a document available to read on EtoBox.

What is Effluent Treatment Plant Progress Report about?

The construction progress of the Effluent Treatment Plant is significantly behind schedule. The contractor, Hindustan Dorr Oliver Ltd., has only completed 27.17% of the work against a target of 71.27%, resulting in a backlog of 43.3%. Manpower at the site is also very low at 235 workers compared to the needed 1000 given the construction delays. An urgent catchup plan is needed to make up the backlog and complete the project before the contractual deadline of March 23, 2012. Improved resources like cranes an