Installation Progress Summary Report by Unclear Project is a document available to read on EtoBox.
What is Installation Progress Summary Report about?
As of September 30, 2024, the installation progress for various steel structures and components shows a total contract volume of 38,870 Kg with an actual volume of 41,101.8 Kg, resulting in a deviation of -1,204.2 Kg and an overall progress of 86.7%. Specific components such as ladders and handrails have lower completion percentages, with 78.1% and 52.6% respectively. The report includes detailed breakdowns of each section
- Author
- Unclear Project
- Language
- EN