Meeting Minutes: Mario Carnaghi Project by Sayantan Dex is a document available to read on EtoBox.
The meeting on September 15, 2025, discussed the contract with M/s Mario Carnaghi for the augmentation of wheel machining facilities, which includes the installation of CNC machines. Key issues included the pending commissioning of the Oil-Hole Drill and the trial runs for VTL-1 and VTL-2, with commitments made by the contractor to supply and install necessary spare parts. The contract value is Euro 44,65,500, with a balance payment of Euro 3,34,913 and Euro 9,000 for repairs.