What is Transformer Construction and Testing Rules about?

Transformers are to withstand a 2 second secondary terminal short-circuit test at rated voltage and frequency without damage. They are to be double wound with dry air cooling, though liquid cooling is allowed if certain safety measures are met. Terminals must be clearly identified and transformers intended for parallel operation must have compatible voltage ratios and short-circuit impedances. Insulation and temperature limits must comply with standards, and transformers undergo high voltage insulation and