Generator and Turbine Installation Steps by yeddidyonatan is a document available to read on EtoBox.
The installation procedure for a T+G turbine generator involves the following key steps over a 90 day period: 1) Preparation work including inspection of the cement foundation, leveling of platforms, and installation of casings and pasderals takes 9 days. 2) Assembly of the turbine and generator components such as installing the stator, checking alignments, and fixing the bottom bearing takes 7 days. 3) Installation of the rotor and subsequent checks of centering, gaps, and bearings takes 8 days. 4)