Can I read DPR Format for Civil Work Progress on EtoBox?

DPR Format for Civil Work Progress by Hurriyat Ali is a document available to read on EtoBox.

What is DPR Format for Civil Work Progress about?

- Earthwork including dumping, grading, compaction and disposal of surplus material was ongoing from RD 0+000 to 0+712. - Pile load testing was completed and declared passed near the existing road. - Retaining wall construction and relocation of utilities was in progress. - Stockpiling of materials at the import yard was ongoing. - Construction activities were hindered by land acquisition problems and relocation/dismantling of existing structures and utilities.