Can I read MDS Tanjung Morawa Progress Report on EtoBox?
MDS Tanjung Morawa Progress Report by Morison Hutabarat is a document available to read on EtoBox.
What is MDS Tanjung Morawa Progress Report about?
This progress report summarizes the construction work done on the MDS Tanjung Morawa building from November 14th to 24th, 2011. Several areas of the building are discussed: 1) On the first floor, 50% of tile installation is complete in the sales area and the red portal in the waiting area has begun to be installed. 2) On the mezzanine floor, tile and piping work is 100% complete in the work area, but gypsum wall installation is only 25% finished. 3) Several issues are noted including incorrect tile use