What is Construction Profit Analysis 2021-2024 about?
The contractor entered into a fixed price construction contract on January 1, 2021 to build a bridge for P144 million. By the end of 2021, estimated costs were P96 million. By the end of 2022, estimated costs increased to P120 million, excluding a contract variation that increased revenue by P2.4 million and costs by P1.8 million. Actual cumulative costs through 2021, 2022 and 2023 (end of contract) were P36 million, P85.26 million and P120.6 million respectively. The contractor uses percentage of completio