Construction Stage Overview and Timeline by hhggsg is a document available to read on EtoBox.
The document compares the master programme for the Minton Condominium project between Revision 3 and Revision 4. It lists the activities, original planned start and finish dates from Rev 3, and the updated start and finish dates from Rev 4. Many activities were delayed by 8 to 31 days in the Rev 4 programme compared to Rev 3. The delays were mainly due to changes in the planned dates for piling works, basement construction, and tower crane installation activities.