Gas Turbine Compressor Water Wash Plan by Ujang Dadang is a document available to read on EtoBox.

The document outlines a plan to conduct a water wash of the gas turbine compressor tag number 920-GTC-101 #A at an FPSO (floating production storage and offloading unit). The plan involves 9 steps: 1) shutting down the gas turbine and allowing it to cool, 2) locking out the process, 3) dismantling parts to access nozzles and replacing filters, 4) preparing a mobile tank with water and chemicals, 5) conducting the water wash, 6) reinstalling parts, 7) cleaning up the area, 8) preparing for a test run, and 9)