7053-Daily Progress Report 04-05-2026 by mtalha alig is a document available to read on EtoBox.

The daily progress report for project PIC I-T-7053 on April 5, 2026, indicates that internal re-inspection of street lighting poles is ongoing, with 208 out of 348 completed. Additionally, reconfiguration of Feeder 2KD06 has been completed, making it ready for energization. The report also notes that there were no inspection hold points and a total of 11 staff were present, with various equipment listed as operational.