Skip to content

Opening book details…

About this document

Dubai Police Training Center Project Update by Najmul Hussain is a document available to read on EtoBox.

The Dubai Police Training Center project is currently at 13.92% physical progress, significantly behind the planned 28.26%. Key delays are attributed to issues with groundwater, discrepancies in drawings, and various construction phases, including substructure and superstructure completion. Immediate actions include addressing groundwater issues, resolving drawing discrepancies, and developing a revised schedule to mitigate delays.

Author
Najmul Hussain
Language
EN