Weekly QA/QC Progress Report by Rifqi Firmansyah is a document available to read on EtoBox.
The weekly work done report from the Directorate General of Water Resources summarizes progress from May 30th to June 12th, 2016. Various construction projects are listed including slope protections at intake towers, shotcrete applications, concrete pouring, and soil testing. The report uses a table to indicate planned versus actual percentages completed for each task on a daily basis over the two-week period. Project advances include 100% completion of slope protections at EL±56.50 and EL±59.40, and 50% fi