Can I read Rampur Hydro Power Station HRT Details on EtoBox?
Rampur Hydro Power Station HRT Details by fini1968 is a document available to read on EtoBox.
What is Rampur Hydro Power Station HRT Details about?
The document summarizes the construction planning of the 15 km head race tunnel for the 412 MW Rampur hydroelectric project in India. Key points: 1. The tunnel will be 15.08 km long with a 10.5m diameter and concrete lining. Rock types along the tunnel include quartz-mica schist, quartzites and phyllites. 2. The tunnel is being excavated through 4 adits using conventional drill-and-blast methods. Construction of one adit was delayed by weak geology, slowing progress. 3. Planning considered using a tunn
- Author
- fini1968
- Language
- EN