Daily Site Movement Report for V.I.V. by Hammaadh Abdulla is a document available to read on EtoBox.
V.I.V Private Limited provided a daily site movement report for construction work on the G.DH Thinadhoo Sports Arena Indoor Complex from April 10, 2016. 12 staff worked from 8 AM to 6 PM, making ceiling frames in the 1st floor kitchen area. Materials used included 5 bags of cement, 10 bags of sand, and 30 bags of aggregate. The report was prepared by Mohamed Rasheed and indicated the project was 27% completed at that time.