eLIMO Phase 1 Work Breakdown Structure is a document available to read on EtoBox.

The document outlines the work breakdown structure for the eLIMO Phase 1 project over 78 days. It involves 6 key stages: 1) Project planning over 6 days, 2) Design and specification of components over 24 days, 3) Preparatory work completed over 11 days, 4) Testing of the electric propulsion system implemented over 57 days, 5) Testing documentation created over 1 day, and 6) Project closed out with final presentation and documentation over 3.2 days.