Can I read Construction Cost Quantity Take-Off Guide on EtoBox?

Construction Cost Quantity Take-Off Guide by angowanv is a document available to read on EtoBox.

What is Construction Cost Quantity Take-Off Guide about?

The document outlines a construction cost estimate for a project involving non-load bearing concrete hollow blocks, including detailed quantity take-offs and labor, equipment, and material costs. The total direct cost amounts to approximately 204,564.50, with additional overhead and profit calculations leading to a total project cost of about 268,490.91. The unit cost is calculated at approximately 952.04 per square meter for the total area to be constructed of 282.015 square meters.