Can I read HNSS Phase-II Package Progress Report on EtoBox?
HNSS Phase-II Package Progress Report by HIMABINDU BANDI is a document available to read on EtoBox.
What is HNSS Phase-II Package Progress Report about?
This document provides a status update on two infrastructure projects - Package 22 & 22BW and Package 23 & 23A of the HNSS Phase-II project. For Package 22, the excavation of the main canal from Km 523 to Km 546 is 80.46% and 58.28% complete for the two agencies working on it. For Package 23, the excavation of the main canal from Km 546 to Km 554 and formation of the Adivipalli Reservoir is 98.92% and 73.74% complete. The document outlines progress, targets, and balances for excavated works, land acquisitio