Can I read HSIA Expansion Project Progress Report on EtoBox?
HSIA Expansion Project Progress Report by Emdad Munna is a document available to read on EtoBox.
What is HSIA Expansion Project Progress Report about?
The document provides a monthly progress report for the Hazrat Shahjalal International Airport Expansion Project for February 2023. Some key details from the report include: 1) The project involves expanding and upgrading the passenger terminal, multi-level car park, and cargo terminals at Hazrat Shahjalal International Airport. 2) As of February 2023, the project was 35 months into the planned 48 month construction period. 3) Work has been impacted by the COVID-19 pandemic, with lockdowns and infectio