About this document
Snag List Report for Room Finishes by Presanna Rajasekaran is a document available to read on EtoBox.
This document contains a site inspection report of the finishing work required for several rooms in a substation. It lists items in the 33kV room, 11kV room, and control and relay room that require work such as epoxy coating of floors, painting of skirtings and walls, repairing cracks and edges, and ensuring equipment is free of paint. The status of each item is listed as "not complied." Photographs may be available to support the findings. Signatures from ONEIC and MZEC staff are required to verify the ins
- Author
- Presanna Rajasekaran
- Language
- EN