Can I read Construction Timeline for Classroom Project on EtoBox?

Construction Timeline for Classroom Project by Salman Hasan Joarder is a document available to read on EtoBox.

What is Construction Timeline for Classroom Project about?

This work plan outlines a 260 day schedule for the construction of an additional classroom at Shubolpur GPS in Damurhuda, Chuadanga, Bangladesh. The plan includes 10 days for site preparation, 45 days for footing works, 90 days for ground floor superstructure, 30 days for roof works, 20 days for electrical works, 30 days for furniture supply, 10 days for environmental works, 15 days for additional items, and 10 days for project handover. The contractor

Author
Salman Hasan Joarder