Can I read Y80 Masantol Tower Project Schedule on EtoBox?
Y80 Masantol Tower Project Schedule by Roy Bernard Basa is a document available to read on EtoBox.
What is Y80 Masantol Tower Project Schedule about?
This document provides a Gantt chart schedule for a telecom tower construction project with the following key details: 1. The project involves constructing a telecom tower in Masantol and has a total scheduled duration of 45 days from August 23rd to October 6th. 2. The schedule is broken down into phases including procurement, foundation construction, and structural steel tower erection. 3. Foundation construction is scheduled from August 27th to September 29th and involves micro piling, footing, and p
- Author
- Roy Bernard Basa
- Language
- EN