MPEB by Avi Maheshwari is a document available to read on EtoBox.

The Supreme Court ruled on the prioritization of power projects based on the least tariff criterion as mandated by the Electricity (Supply) Act, 1948, stating that the Madhya Pradesh Electricity Board (MPEB) acted within its rights to negotiate terms with independent power producers (IPPs). The court found that the agreements were not statutory contracts in their entirety, as the obligation to maintain escrow accounts was contingent on mutual agreement rather than a statutory requirement. Ultimately, the co