FRP Panel Tank Installation Schedule by tofa is a document available to read on EtoBox.
This document outlines the production schedule for fabricating and installing two fiberglass reinforced panel tanks with capacities of 40m3 and 60m3 for customer Wijaya Karya. The schedule spans from August to October 2016 and includes tasks for design, material procurement, fabrication at the shop, delivery to the site, installation, and inspection. Key tasks include layer lamination in August, fabrication of the panels in September, delivery and mobilization in early October, setting of the panels and com