Haven Residence Daily Report 12/17/2025 by phyo7799 is a document available to read on EtoBox.
The daily report for the Haven Residence project on December 17, 2025, indicates that the project is on day 200 of a 573-day contract period, with an estimated completion date of December 25, 2026. Various construction activities were carried out, including wall plastering, installation of conduits, and site cleaning, with a total workforce of 130 on-site. Material deliveries included significant quantities of AAC blocks, cement, and other construction supplies.