The 268th Flash Report provides an update on 515 infrastructure projects across various sectors costing over Rs. 100 crore each. During the month, 3 new projects were added and 1 was deleted. 123 projects reported additional delays of 1-48 months due to issues like equipment delays. Key delays were reported in the steel, power, petroleum and road transport sectors. The total cost of implementing the 515 projects is estimated to be over Rs. 26 lakh crore, with 224 projects currently delayed from their origin