Can I read JBG Building Re-Tuning Case Study on EtoBox?

JBG Building Re-Tuning Case Study by thamer al-salek is a document available to read on EtoBox.

What is JBG Building Re-Tuning Case Study about?

The JBG Companies implemented building re-tuning and upgraded pneumatic controls to direct digital controls at their 275,000 square foot building located at 7200 Wisconsin Ave in Bethesda, MD. Re-tuning measures identified by Pacific Northwest National Laboratory experts and implemented by JBG engineers resulted in a 1% reduction in projected electricity usage despite increased occupancy and usage. Re-tuning identified opportunities like adjusting temperature setpoints and schedules, improving economizer us