Bored Piling Method Statement by Adonis Alabi is a document available to read on EtoBox.

The document provides work procedures for bored piling installation. It outlines 8 key steps: 1) submitting method statements and plans for approval, 2) submitting a construction program, 3) getting approval for piling sequence, 4) setting out locations, 5) submitting source certificates, 6) concrete cube testing, 7) pile testing, and 8) inspection and documentation using a checksheet. The contractor must follow these steps and obtain necessary approvals at various stages of the piling work.