SUKE Elevated Expressway Daily Report by KumaResan Subramaniam is a document available to read on EtoBox.
1) Piling work continued at Section 2, with a pile at MB10 hitting rock at 8.1m and continuing the rock socket to 16.1m. Rebar installation also ongoing for another pile cap. 2) A pile at MB30 hit rock at 16.8m and bore a 3m rock socket, with pile caps being constructed - one lift cast and rebar installation ongoing for another. Sheet piling start for a third pile cap. 3) Daily activities including housekeeping and machinery unloading are reported, along with manpower, machinery and materials details.