Cukai Sentral Project Progress Report by asyraf zaidi is a document available to read on EtoBox.
What is Cukai Sentral Project Progress Report about?
This document provides a progress update for the Central Customs Development Project in Kemaman, Terengganu, Malaysia. It outlines 38 tasks related to physical and non-physical works, including site surveys, temporary relocation of services, equipment procurement, and contractor plant rental over the projected 755 day duration. The project is currently tracking slightly ahead of schedule at 21.49% complete, within budget and on track for the planned completion date of February 21, 2024.
- Author
- asyraf zaidi
- Language
- EN