Jetty 2 Trestle Restoration Costs by Muhammad Fachrureza is a document available to read on EtoBox.

This document outlines a master schedule for rectification works on Jetty 2 Trestle from November 2021 to March 2022. It includes two main phases: 1) Indirect Cost/Preparatory Works lasting 84 days, including mobilization, preparation works and project management. 2) Direct Cost/Steel Structure Rectifications lasting 65 days, including scaffolding installation, removal and renewal of baseplate supports, welding inspections, installation of new members, and cutting/patching works. The schedule provides timel