Can I read Monthly Progress Report No. 32 Summary on EtoBox?

Monthly Progress Report No. 32 Summary by Premier Toh is a document available to read on EtoBox.

What is Monthly Progress Report No. 32 Summary about?

As of June 25, 2019, the overall physical progress of the project is at 87.39%, which is 4.61% behind the planned target, while financial progress is at 88.11%, 2.89% below expectations. Key activities include ongoing earthworks, pavement, drainage, sewerage, and water reticulation tasks, with some completed and others still in progress. The revised completion date for the project is now set for August 8, 2019, due to crop counting and compensation issues.