Discounted Payback Period Analysis by Muskaan Gupta is a document available to read on EtoBox.
Project A and B are being evaluated. Project A has a payback period of 1.6 years and discounted payback period of 1.9 years with a discount rate of 12%. Project B has a payback period of 2.25 years and discounted payback period of 2.6 years with a discount rate of 12%. The net present value (NPV) of Project A is Rs. 2,500 with an internal rate of return (IRR) of 28%. The NPV of Project B is Rs. 3,000 with an IRR of 22%. Project C has an NPV of Rs. 0 with an IRR of 0%.