Flowline Excavation Safety Analysis by Roy Hage is a document available to read on EtoBox.

This document provides a Job Safety Analysis for excavation and construction works involving crossing existing pipelines. It identifies potential hazards at each step of the work and lists corresponding hazard controls. The six basic steps analyzed are: 1) obtaining work permits, 2) securing the work area against traffic, 3) hand excavating around pipelines, 4) excavating deeper than 4 feet, 5) installing temporary pipe protection, and 6) excavating using heavy equipment. Hazards include struck by vehicles,