Can I read Mechanical Completion Timeline on EtoBox?
Mechanical Completion Timeline by SARAVANAN ARUMUGAM is a document available to read on EtoBox.
What is Mechanical Completion Timeline about?
This document provides a schedule for the Borouge 4 Project - EPC Package 4 from February 2023 through October 2023. It involves HDPE piping works and related laying works over 190 days. Key milestones include contract award, mobilization, mechanical and civil completion, commissioning, and site handover. The schedule outlines activities such as engineering, procurement, equipment mobilization, site survey, and site execution work including mechanical and civil tasks in three priority groups from February t
- Author
- SARAVANAN ARUMUGAM
- Language
- EN