Khalifa City Infrastructure Project Status by layeeqit57 is a document available to read on EtoBox.
The document outlines the status of the road and infrastructure development project at Khalifa City, with a total of 44 general snags identified, of which 37 have been closed, resulting in an overall closure percentage of 84%. There are currently 7 open issues related to incomplete installation and energization of feeder pillars and cabling work across various locations. The project is awaiting clearance from ADDC to proceed with final testing and activation of lighting and small power functionalities.